Anhui: Ground-based distributed photovoltaics are included in index management (excluding self-owned land), and household use is filed by the enterprise (except for full payment)

Time:

Sep 14,2023

Source:

Author:

On August 26, the Anhui Provincial Energy Bureau issued the "Notice on Further Promoting the Orderly Development of Distributed Photovoltaic Standards", which gave new requirements for distributed photovoltaic management.

The document points out that new ground photovoltaic power stations with a record of less than 6 megawatts (including photovoltaic power station projects built using pit pond water surface, combined with agricultural greenhouses, livestock breeding, etc.) are included in the annual construction scale management, and projects not included in the annual construction scale shall not start construction or be connected to the grid.

Single point access less than 6 MW of industrial and commercial distributed photovoltaic projects (refers to the use of industrial and commercial enterprises own construction land within the scope of the roof or ground construction of distributed photovoltaic) and household photovoltaic projects, temporarily not included in the annual construction scale management.

Natural person full purchase mode household photovoltaic projects by the power grid enterprises on behalf of natural persons to apply to the local energy authorities for the record, other distributed photovoltaic projects by the roof property owners independently choose investment and development enterprises, by the investment and development enterprises to apply for the record, the record scale in principle for the exchange side capacity.

Full purchase mode household photovoltaic in the name of a natural person to apply for power grid access, power grid enterprises before the grid should be confirmed by verifying the identity of the applicant's natural person and the main photovoltaic power generation equipment (including photovoltaic modules, inverters, etc.) purchase invoices and other means.

The project should be organized by the power grid enterprises network-related equipment acceptance and commissioning after the grid operation, by the power grid enterprises in accordance with the regulations unified scheduling, the new distributed photovoltaic should have considerable measurable controllable adjustable function, the existing distributed photovoltaic gradually transformed with the corresponding function.

In addition, less than 6 MW of ground photovoltaic power stations that have been filed before the issuance can start construction after the implementation of the grid access conditions, and those that have not been connected to the grid before the end of December 2023 will be managed according to the new project.

See below specifically: