Dingbian Longpan Photovoltaic Power Station Project
Located in Dingbian County, Shaanxi Province, the site is located in the sandstorm saline-alkali beach area. The total capacity is 30MW and the total investment of the project is 300 million yuan.
Construction started in September 2021, the first grid connection in December 2021, and the full capacity grid connection in May 2022. It can provide 43.72 million kW · h of clean electricity to the grid every year. It can reduce CO2 emissions by about 44100 t, SO2 emissions by about 335.2t, NOX emissions by about 1801.5t each year, and reduce the corresponding wastewater discharge, which has significant energy saving and emission reduction benefits.